10 Minute Tip - Scheduled reports sending multiple emails


Today we will discuss a couple of reasons why your users may be receiving multiple emails for a single scheduled report from Maximo. For example, the user has a weekly report sent to them yet, for some unknown reason, they get 2, or more copies of the report in their inbox. The "unknown" reason is usually one of two things.

  • It's actually not a duplicate. Since scheduled reports do not indicate anywhere in the email where they came from - which Maximo server - we have seen times when the second email is actually not coming from the Production Maximo server. Perhaps they are testing functionality from a test server, or maybe a Sandbox server is being used and the same user has the same report set up on that server and the extra email(s) they are receiving are, in fact, being sent from this other server.  Double check the other servers - you can use the View Scheduled Reports option from Report Administration to aid in this effort.  One suggestion we have that may help is to put the server name in the email Subject or Comments section when the report is scheduled.


  • The other known possible cause is related to the fact that a complex report that takes extra time to process will appear to Birt to be hung and it will restart it. Eventually these newly spawned jobs will all finish  and the emails will all be sent.  By default if the RUN phase of a report (the SQL phase) takes longer than 15 minutes the issue can present itself.  This 15 minute setting can be changed so if you feel this is the issue (and you can verify this usually be checking the report usage log to see how long the report took to complete)  you can change it as follows:

Goto -> System Configuration/Platform Configuration/Cron Task Setup
Select -> REPORTLOCKRELEASE cron task
Change Parameter-> LOCKINTERVALINMINUTES to the desired value - say 30, for example
Save changes
Restart the Maximo Application server to ensure new value is activated


There's generally no repercussions to making this change but bare in mind that it's for all scheduled reports. There is no ability to change it for specific reports.

In most cases the multiple emails are caused by one of the above situations.

That's all for now.